Statement of Work
For Human Resource/Consultant Database Management System (HRDBMS)

 

The information and Date in these pages are property of JSMN International, Inc. and shall not be disclosed beyond JSMN International without the prior approval of JSMN International, Inc.

 

Version 3.0
Document Date: February 14, 2007

 

Document Control Information

 

Approvals:

 

Dept

Name

Date

Prepared By

IT Dept

Mr. Ram Nunugonda

14-Feb-2007

Reviewed /
Approved By

Technical Assessment

Business Finance

Mr. Ravinder. T

 

Mr. Ravinder. T

21-Feb-2007

 

21-Feb-2007

 

Revision History:

Version Number

Revision Date

Description of Changes

Location (Page, Para/Sec.Nos)

 

 

 

 

 

 

 

 

 

 

 

 

 

Copy Number:

Currency Statement

  1. It is a controlled soft copy if it is maintained on-line in a controlled area
  2. It is an uncontrolled copy if it does not satisfy the above conditions

  

Definitions & Acronyms

 

 

These are the definitions and acronyms used in this SOW. They are group and project specific acronyms.

 

Term of Acronym

Definition

AID

Application Information Document

ASP

Application Specific Plan

PM

Project Manager

ADO

Application Development Objective

ADC

Application Development Center

IRN

Internal Resource Network

PSM

Production Support Manager

PCO

Project Coordinator

SOW

Statement of Work

ADT

Application Development Team

UAT

User Acceptance Test

BAT

Business Analyst Team

ICA

Inter Company Agreement

 

Table of Content

1.0  Executive Summary
2.0  Statement of Work
2.1 Introduction
2.2    References
2.3    Key Assumptions
2.4    Scope Of Work
2.5    Project Tasks
2.5.1      Project Management Services
2.5.1.1       Setting up of ADC Center
2.5.2      Staff Supplementation Services
2.5.3      Project Completion
3.0  JSMNIT Responsibilities
3.1    Project Management
3.2    Project Organization10
3.3    Project Office – Roles & Responsibilities
4.0  JSMNHR Responsibilities
4.1    Project Management
4.2    General Responsibilities
4.3    Database Content
4.4    Laws, Regulations and Statutes
4.5    Space and Facilities
4.6    Security
5.0        Project Coordinators
5.1 For JSMNHR
5.2    For JSMNIT
6.0        Hardware/Software/Tools/Communication Requirements
10.0  Estimated Schedule
11.0  Staffing Plan / Skills
12.0  Charges
13.0  Change Control Procedure
13.1       Project Change Request Form
14.0  Agreement

 

 

1.0  Executive Summary

This Statement of Work (SOW) defines the scope of work to be accomplished and the tasks to be performed by JSMN International, Inc information technology department (herein after referred as JSMNIT) for JSMN Human Resource Department (herein after referred as JSMN HR) under the terms and conditions of the applicable versions (current versions or future versions as and when rolled out/made applicable) of the JSMNIT Framework Agreement and JSMNHR Provider Attachment.
In the event of any conflict among the terms and conditions of the Framework Agreement, the Provider Attachment and the Statement of Work, the following order of precedence will prevail:

This project will involve the JSMNIT team and JSMNHR Department.

On completion of successful knowledge transition, the JSMNIT will follow the JSMNHR processes to execute the technical deliverables as per the priorities set by JSMNHR Dept. In the absence of clearly defined processes, JSMNIT will work with the Human Resource Department in establishing mutually agreed procedures.

The tasks to be performed by JSMNIT have been referred to as "JSMNIT Responsibilities" in this SOW. It is the responsibility of JSMNHR to fulfill its responsibilities and obligations as stated under various Sections of this SOW.

The current place of work for this assignment is JSMN International, Inc at New Jersey, USA.

JSMN International, Inc, reserves the right to change location for development team in case of space crunch at the location. JSMN HR will work out JSMN International, Inc’s Jersey City, Office.

 

2.0  Statement of Work

2.1 Introduction

This SOW defines the scope of work to be accomplished by JSMNIT and specific responsibilities for various activities / tasks planned to be performed and completed by JSMNIT with inputs from and / or participation of JSMNHR. It will be the joint responsibility of JSMNIT and JSMNHR team to complete the entire project defined in this SOW, subject to various terms and conditions specified in this SOW and various assumptions given below. The successful completion of this SOW depends upon the full commitment and participation of JSMNHR.

Changes to this SOW will be processed in accordance with the procedure described in the section Change Control Procedure.

References

The current applicable/published highly confidential versions of the referenced documents are the following:

  1. JSMNIT Framework Document V3.0.pdf
  2. JSMNHR Requirement Document

Key Assumptions

While preparing this SOW the following key assumptions have been made. Any change in the following assumptions may have an impact on cost, schedule, approach and staffing plan in the SOW, which will be managed through Change Control Procedure as applicable.

 Scope of Work

This section describes the scope of services to be performed by JSMNIT under this SOW for providing Application Development & Management Services for the in-scope applications. The scope of services to be performed is based on the following sections and is subject to the assumptions made in the section Key Assumptions. Tasks to be performed by JSMNIT are outlined in the section JSMN Responsibilities. The tasks to be performed and/or deliverables to be provided by  JSMNHR to enable JSMNIT to discharge the responsibilities are listed in the section JSMNHR  Responsibilities.   

Scope of services includes:

  Project Tasks

This section details the tasks to be performed during the life of the project. The responsibilities of the tasks are defined below.  The Change Control Procedure will control any deviation that has a potential impact on the project.

Project Management Services

Task Objective:
JSMNIT will provide Project Management, development and maintenance services and resources, to fulfil its obligations under this SOW. Prior to the start of the Project, JSMNIT will identify and appoint an individual responsible for the performance of the services known as the JSMNIT Delivery Project Manager.  The purpose of this activity is to provide technical guidance and managerial control of JSMNIT project personnel and to provide a framework for project planning, communications, reporting, process adherence and contractual activity. The responsibilities of the JSMNIT Delivery Project Manager are:

JSMNIT, in conjunction with JSMNHR, will establish a regular and comprehensive schedule of project meetings, and reviews.
JSMNIT will report to JSMNHR and JSMN Operations Department as soon as possible on any perceived or anticipated problems, with associated recommended resolution, which may have significant impact on the costs.
Completion Criteria:
This activity will be completed when the end date of the project as mentioned in the section "Estimated Schedule" is reached or Project is completed as stated under Section “Completion Criteria”, whichever is earlier.

Setting up of ADC Center (Application Development Center)

Task Objective
The objective of this task is to set up the necessary infrastructure at the JSMNIT ADC location.  During this task the connectivity to JSMNHR server from the ADC center is established to enable start of services from the ADC location.

JSMNIT Responsibilities

 

JSMNHR Responsibilities

JSMNIT Deliverables

 

Completion Criteria
This activity is complete when JSMNIT informs JSMN Operations Department and JSMNHR of necessary infrastructure having been established at JSMNIT ADC.

Staff Supplementation Services

Task Objective:
The objective of this activity is to provide project management and staff augmentation support to JSMNHR as required for the projects.

JSMNIT Responsibilities

JSMNHR Responsibilities

JSMNIT Deliverables:

Completion Criteria
This activity will be complete when the end date of the project mentioned under Section, ‘Estimated Schedule’ is reached or Project is completed as stated under Section “Completion Criteria”, whichever is earlier.

Project Completion

Task Objective
The objective of this task is to declare the Project End.
JSMNIT Responsibilities

JSMNHR Responsibilities